In the next six weeks, The Outlook at Windhaven (OAW) construction progress will include:
- Finish ceiling system and continue finish out in Commons building
- Continue finish out of first set of Independent Living (IL) apartments
- Begin finish out of second set of IL Apartments
- Begin finish out of the Assisted Living/Memory Support (AL/MS) units and common spaces
- Continue exterior façade work on IL building
- Continue landscape and hardscape of Community Courtyard, located between Commons and AL/MS buildings
- Continuing landscape and hardscape around Commons building and IL Pool Courtyard
![](https://theoutlookatwindhaven.org/wp-content/uploads/2024/04/Commons-Bldg-Main-Entry-1024x768.jpg)
![](https://theoutlookatwindhaven.org/wp-content/uploads/2024/04/Main-Entrance-Living-Room-1024x768.jpg)
![](https://theoutlookatwindhaven.org/wp-content/uploads/2024/04/Fitness-Room-1024x768.jpg)
![](https://theoutlookatwindhaven.org/wp-content/uploads/2024/04/IL-Dining-and-Private-Dining-Rooms-1024x768.jpg)
![](https://theoutlookatwindhaven.org/wp-content/uploads/2024/04/Community-Courtyard-and-AL-Dining-Porch-1024x768.jpg)
![](https://theoutlookatwindhaven.org/wp-content/uploads/2024/04/Terrace-1024x768.jpg)
![](https://theoutlookatwindhaven.org/wp-content/uploads/2024/04/IL-Apartment-1024x768.jpg)
![](https://theoutlookatwindhaven.org/wp-content/uploads/2024/04/Pool-Courtyard-Progress-1024x768.jpg)