In the next six weeks, The Outlook at Windhaven (OAW) construction progress will include:
- Nearing completion of the following spaces in Commons building: living room, administrative and dining areas, commercial kitchen and back of house spaces
- Continue finishes in residences and common spaces of Assisted Living/Memory Support (AL/MS) building
- Continue finishes on first and second sets of Independent Living (IL) apartments
- Continue finishes on Fitness Center
- Finish framing and mechanical, electrical, plumbing (MEP) rough-in of pool enclosure
- Nearing completion of landscaping and hardscaping of Community Courtyard, located between Commons and AL/MS buildings
- Continue landscape and hardscape around Commons building and IL Pool Courtyard