In the next six weeks, The Outlook at Windhaven (OAW) construction progress will include:
- Installation of drywall in Commons, first set of Independent Living (IL) apartments and Assisted Living/Memory Support (AL/MS) residences
- Continuation of interior finish work for Cottages
- Continuation of hardscaping and landscaping for Cottages
- Beginning and continuation of exterior façade finishes for Commons, IL and AL/MS buildings
![](https://theoutlookatwindhaven.org/wp-content/uploads/2023/12/Commons-IL-and-ALMC-Buildings-Progress-1024x768.jpg)
![](https://theoutlookatwindhaven.org/wp-content/uploads/2023/12/Cottages-Progress-1024x768.jpg)
![](https://theoutlookatwindhaven.org/wp-content/uploads/2023/12/IL-Dining-Room-1024x768.jpg)
![](https://theoutlookatwindhaven.org/wp-content/uploads/2023/12/Hallway-to-Fitness-Room-and-Pool-House-Entry-768x1024.jpg)
Pool House Entry
![](https://theoutlookatwindhaven.org/wp-content/uploads/2023/12/Main-Hallway-768x1024.jpg)
![](https://theoutlookatwindhaven.org/wp-content/uploads/2023/12/IL-Pool-Courtyard-1024x768.jpg)