In the next six weeks, The Outlook at Windhaven (OAW) construction progress will include:
- Finish framing Independent Living (IL) and Assisted Living/Memory Care (AL/MC) buildings
- Set windows in Commons, IL and AL/MC buildings
- Waterproof Commons, IL and AL/MC buildings
- Run mechanical, electrical and plumbing engineering (including heating, ventilation and air conditioning) through Commons, IL and AL/MC buildings
- Continue exterior finish work for Cottages
- Begin interior finish work for Cottages